Weather permitting, on-going construction on several of Laredo’s industrial street projects will include several closures, starting next week. The City of Laredo contractor will coordinate with area businesses to maintain access. The traveling public should slow down, drive with extreme caution, and observe all safety signs, traffic control devices and flaggers in the work zone area.
Killam Industrial Park
Work will continue on the intersection of Killam and Archer, and Sara and El Gato. El Gato will remain closed at Sara, traffic must be detoured to Whitepoint Road. Traffic on Archer must yield to traffic turning from Killam Avenue. Flaggers will also be used at these intersections during most day time operations.
Beginning Tuesday, June 1, work will begin on Killam between Lamar Road and FM 1472. Traffic will be switched to one lane each direction on Killam.
Inter-America Industrial Park
Work will continue at intersection of Inter-America and FM 1472 entrance for approximately the next two weeks.
On Wednesday, May 26, work will begin on a short section of Pan American road about half a mile west of FM 1472. Traffic will be transition to one side of the roadway.
Tejas Industrial Park
Work will continue on San Mateo Avenue while traffic will be transitioned to one side of the road.