Water line replacement schedule for Maher-Bustamante intersection

Qromex, a private contractor hired by the City of Laredo, will temporarily cause traffic inconvenience at the intersection of Maher Avenue and Bustamante Street in order to install a 24-inch waterline.

Construction is scheduled to begin Monday, Feb. 14, from 8 a.m. to 5 p.m.

Water services will not be interrupted at this time. Affected properties in this area will be notified by the contractor at least 24 hours before water shut-off.

The replacement of the water line is anticipated to take about three weeks for completion. Progress updates will be made available by the Utilities Department.

Motorists and pedestrians traveling through the area are cautioned to heed all posted traffic control signs and devices to provide safety to all citizens.